Upcoming Frankfurt infrastructure maintenance on July 4, 2023. The following 3 servers will remain down for 8 hours.

 
Quote:
===
In the coming period, Leaseweb will move all services from FRA-10 to the new state-of-the-art Iron Mountain datacenter (FRA-01) in Frankfurt.
 
Therefore, we will need to perform scheduled maintenance on part of our infrastructure.
 
WHEN CAN YOU EXPECT IT
Timezone: CEST (UTC+02:00)
July 04, 2023 09:00 - July 04, 2023 17:00
Duration: 8h
 
WHAT IS THE IMPACT ON YOUR SERVICE?
Your dedicated server(s) will be physically migrated to the FRA-01 datacenter to retain the IP addresses for your dedicated server. The server will be offline during the maintenance window. Please be assured that we will do our utmost best to keep the downtime as minimal as possible, and our engineers are available during and after the migration should any issues arise.
 
Server(s) impacted by the migration:
  • Dedicated Server - Intercrus
  • Dedicated Server - Veritate
  • Dedicated Server - Tucana

===

Kind regards & datalove